|
The last stand
Newry-based John Tinnelly
& Sons Ltd. were responsible for the demolition of the Hogan Stand. Here
we talk to Joseph Lonergan and Austin OıHare about the companyıs involvement
in the latest phase of Croke Parkıs development.
There has been a noticeable change in the skyline around Jones Road
of late. The third phase of the development of Croke Park, which commenced
the week after last years All-Ireland ladies showpiece between Mayo
and Waterford, included the demolition of the Hogan Stand and rubble is
all that remains of the 16,000 seater double-decker. Work on its replacement,
a replica of the Cusack Stand, has already begun and it will link the
new stand on the far side of the pitch and the stand at the Canal End.
This is the third time the best known stand in Irish sport has undergone
a facelift. It was originally built in 1924 and, by present day standards,
was a modest, small wooden structure with a seating capacity of 1,400.
The stand was, of course, dedicated to the memory of Michael Hogan, the
Tipperary footballer who had been shot dead by the Black and Tans while
representing his county against Dublin on 21 November, 1920.
Construction on the stand as we knew it began in 1957 and, when completed
two years later, it replaced both the old Hogan Stand and the Long Stand.
The Railway Cup hurling final of 1959, between Munster and Connacht, marked
its official opening. The legendary Christy Ring stole the show on that
occasion, scoring 4-5 as the southern province lifted the crown. Incidentally,
the old structure was relocated to Limericks Gaelic Grounds and
it remained there until the construction of the Mackey Stand which was
officially opened in 1988.
The development of Pairc An Chrocaigh into one of the worlds premier
sporting venues is the jewel in the crown of the GAAs evolution.
The cost of the entire project will be in the region of £150 million
and, when completed, will boast a spectator capacity of approx. 84,000
and will be the envy of all other sporting organisations.
All at Tinnelly Demolition, the company responsible for the demolition
work on the Hogan Stand, are, understandably, proud of their contribution.
Even when walking along the front of the empty stand, prior to commencement
of demolition, you could almost detect the deafening resonance that would
have greeted past finalists, remarked Contracts Surveyor Joseph
Lonergan. Associated too, with such memories, would have been the
unforgettable commentary of Micheal O Hehir.
Contracts Manager Austin OHare added: Were very proud
to be associated with this development and the GAA. When completed, Croke
Park will be able to take its place amongst the finest stadia in the world.
It will be a stadium that all its members can be proud of and we are,
like everyone else, really looking forward to seeing it in its new glory.
Demolition of the Hogan Stand presented a formidable challenge to John
Tinnelly and Sons Ltd.. Its close proximity to the adjacent works and
that of other properties, including the railway, necessitated meticulous
pre-planning by contracts management prior to work commencing.
The principal components comprised 15,000 tonnes of densely reinforced
concrete supporting some 400 tonnes of steel frame and roof, all enclosed
with 6,500m of asbestos cement sheeting.
Removal of the latter was the first major task, explained
Austin. All the sheeting had to be carefully dismantled and lowered
by crane to a prepared base, where it was immediately double wrapped and
transported to a licensed disposal location in Germany. Continuous air
monitoring took place over this stage of the work and at no time was there
ever an occurrence of hazardous airborne dust.
Subsequent to the asbestos removal, all steelwork was taken down in sections
after being cut away by oxy/propane torches. Finally, the concrete structure
was systematically broken away and removed.
Reassuringly, in these days of environmental awareness, the steel frames
and majority of reinforcement was cut to manageable sections, loaded and
exported to England for recycling. In addition, the concrete, when broken
up, was transported off site for crushing and re-use in suitable projects.
Established in 1959, John Tinnelly and Sons Ltd. has successfully undertaken
many large scale demolition projects ranging from sports stadia to factories
to high rise dwelling blocks. In addition to demolition, they also provide
the specialist services of asbestos analysis and removal as well as facade
retention. It is not without justification that the Company objective
is that of providing Demolition at the Cutting Edge.
The demolition of the Hogan Stand is one further success story in the
history of work undertaken by the ever burgeoning Newry-based company.
Great pride is taken in completing such a contract within programme
and without incident, in terms of health and safety, remarked Austin.
This achievement has been due, in large, to the excellent team spirit
developed between John Sisk and Son Ltd. (the developments main
contractors) and ourselves.
Everything is going extremely well for the company at the moment.
Weve a lot of work already on the books while were continuously
tendering for more. Were looking forward to a very good 2000.
Patrick Tinnelly is MD of Tinnelly Demolition and is an active member
of the St. Bronaghs club in Rostrevor, home of Down county stars
Peter McGrath (manager), Finbarr Caulfield, Aidan Farrell, Liam Austin
and Leo Murphy. Many members of the company also follow the fortunes of
the Rostrevor club. Needless to say, they are all are looking forward
to a Mourne County All-Ireland success in front of the newly erected Hogan
Stand in 2001!
|