|
Stadium
of might
The redevelopment
of Croke Park has transformed the spiritual home of gaelic games into
a modern day phenomenon. Even today the half finished stadium exudes presence
and when it is finished the new stadium will be simply awesome.
Croke Park is already considered one of the finest stadiums in Europe
and when the final touches are put into this 80,000 seater stadium it
will be even more impressive.
Seamus Monahan & Partners, Chartered Quantity Surveyors and Construction
Project Managers, first became involved with the redevelopment project
back in 1990. Initially the brief was for Quantity Surveying services
only. However, given the immense scale of this flagship project, it was
quickly established that a dedicated project management team was essential
to ensure the smooth running of the project. SMP were appointed to fulfil
this role in 1991 and since then Chris Gogarty and his team have worked
hard in bringing this project through to completion.
As Project Managers SMP are responsible for co-ordinating all aspects
of this ambitious project. The Project Management team act as the main
point of contact between the GAA administration and the rest of the project
team. By working closely with the Association, SMP establishes the precise
requirements of the GAA and communicates these requirements to the architects,
engineers and contractors. Furthermore our aim is to ensure that these
requirements are met in terms of budget and programming notes Chris.
One of the most challenging aspects of this project is the fact that the
stadium must remain in use throughout the redevelopment. With Croke Park
very much in demand each summer, all works must be carried out in a manner
which fits in with the heavy games schedule. Due to this factor,
explains Chris, the programmes tend to run from the end of one years
All-Ireland to the commencement of the following years championship. For
example, work began on the Hogan Stand after last years All-Ireland finals
and we now have a substantial part of the lower tier available for this
years finals.
While also acting as Quantity Surveyors for the project, SMP takes responsibility
for the cost of the entire construction project from start to finish.
This includes the administration of the tender process, right through
to managing the on going costs and bringing the project in on budget.
Initially the project was perceived as a step by step process rather than
a continuous one. However, with government assistance, the GAA have been
able to step up the momentum to a stage where the Hogan Stand commenced
prior to the completion of the Canal End.
Phase one (the Cusack Stand) was completed on programme and within budget.
In fact the original target for the first year was exceeded. The plan
was to have the one tier of seats ready for the All-Ireland semi-finals
in 1994 but in fact 10,000 seats were available for the Leinster football
finals that year.
According to Chris, phase 2 (the Canal End) has not progressed as smoothly
due to a number of factors beyond SMPs control. Delays were caused
by a series of industrial disputes last year which when compounded with
the scarcity of resources within the industry at present means that the
completion of the Canal End is behind schedule.
Phase 3 (the Hogan Stand) began in October and is progressing well with
a substantial part of the lower tier available for this years All-Ireland
finals. This phase is scheduled for completion by the end of 2001.
The final phase, the Northern End, is still at the early design stage.
This will be the most difficult phase given the proximity of the railway
line and the general shape of the available ground. At present the stadium
has been designed in a horseshoe shape with the Hill left as an uncovered
area. Options for this area are still under consideration.
Seamus Monahan & Partners, Chartered Quantity Surveyors, was established
in 1961 and expanded rapidly to establish a reputation as one of the leading
building cost consultancy practices in the country. In response to a demand
from existing clients SMP developed a separate Construction Project Management
Consultancy in the late 1980s.
SMP have a wide and varied client base and have expertise in a wide range
of construction projects. Recent projects include Blanchardstown Shopping
Centre, the new TV programmes building at RTE, TG4 studios and transmission
network and office developments at Sandyford and Blanchardstown. Other
notable leisure projects include acting as Quantity Surveyors for the
redevelopment of Lansdowne Road for the IRFU in the early eighties.
Obviously, the Croke Park redevelopment is one of the biggest projects,
which the company has worked on to date in terms of scale and complexity.
This is a major project with a very high profile and we are very
proud to be involved, Chris points out. SMP are involved in
a wide range of other projects both big and small and we dedicate the
same enthusiasm and professionalism to all of our clients.
SMP look forward to continuing our now long standing relationship
with the GAA in the future, but for now we are concentrating on completing
the current phases in Croke Park says Chris. Its a marvellous
project for the GAA and I have huge admiration for the Association for
having the vision and confidence to proceed with such a major undertaking
and to do so successfully. They have led the way in terms of stadium redevelopment
in this country and when Croke Park in complete they will be seen to have
led the way in the UK and Europe as well. In terms of the architecture
and design, Croke Park can match any stadium Ive seen anywhere in
the world.
Amazingly the dream is fast on its way to becoming a reality. However,
before that is finally accomplished, Chris Gogarty and the entire project
team will be spending another couple of long summers in Croke Park. Someones
gotta do it.
|